High-Level Overview of the Nordic Flow-based Process

The Nordic Flow-Based (FB) capacity calculation process is regulated by Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity allocation and congestion management (CACM) framework and is carried out by the Nordic TSOs and the Nordic RCC.

Process steps:

Explained in execution order

CGMA (Common Grid Model Alignment)
The Day-Ahead (DA) process begins at 16:30 on D-2 with the Nordic Common Grid Model Alignment (CGMA). At this stage, no market results are available for the D-2 horizon, so a coherent Nordic view of the system is needed.

The Nordic TSOs provide the Nordic RCC with forecasts for demand, generation, HVDC capacities, and network capacities. The Nordic RCC then calculates a reference case containing net positions and cross-border flows across all Nordic bidding zones.

For the following capacity calculations, market results are available and form the reference case for the remainder of the process. Therefore, CGMA is only used in the D-2 process.

IGM (Individual Grid Model)
Each TSO creates an IGM based on the above described reference case. The IGM represents the expected operation of the national power system, including topology, generation, load, and operating conditions.

CGM (Common Grid Model)
The Nordic RCC combines all IGMs into a Common Grid Model (CGM), providing a unified representation of the Nordic power system.

CCC (Coordinated Capacity Calculation)
TSOs provide the Nordic RCC with additional data containing CNE/CNEC data, remedial actions (RA), already allocated capacities (AAC) (like the xFFR), and HVDC capacities. Using the CGM and this additional data, the Coordinated Capacity Calculator (CCC) calculates the FB domain.

Validation and publication
Afterward the FB domain is to be validated by each of the TSOs. Any TSO can choose to reject the domain and instead update their input data, the IGM and/or the additional data, which will rerun the rest of the process.

When all TSOs have accepted the domain its published on the JAO Publication Tool (PuTo).

Market Coupling
The FB constraints are used in the European market coupling process. The algorithm determines prices and traded volumes in each bidding zone while ensuring that all flows remain within the calculated constraints.

Substitution

If one of the above steps fails, a backup measure is initiated depending on the failed step. The Nordic TSOs can substitute IGMs, CGMs and FB domains with files from another day.

A substitution of the full FB domain is called a backup domain. Details of FB domain backups is published on JAO PuTo.

Timings

Day-Ahead Process (D-2) Preliminary Domain
The DA process starts on D-2 at 16:30 with the CGMA step. During the evening, the IGM, CGM, and CCC processes are completed, followed by TSO validation of the domain. The preliminary domain is typically validated and published on JAO PuTo around 21:00 on D-2.

The preliminary domain is currently published for transparency purposes only and is not used in any market process.

Day-Ahead Process (D-2) Final Domain
In the morning of D-1, the calculation of the DA domain continues. The process starts with the D-2 CGMA, but TSOs can update their IGMs with new information, such as forecast revisions and grid changes. The updated IGMs are merged into a CGM, followed by the CCC step, where capacity market reservations are included.

After TSO validation, the final DA domain is published at 09:30 on D-1. In case of significant grid changes, capacities can be updated until 11:00 on D-1.