Svk will adjust the safety margin (RM) on selected critical grid elements in accordance with the Nordic CCM Article 3.

The change means that FRM values are adjusted -7 to 2% of the maximum capacity based on operational experience and methodological calculations for the safety margin. These new safety margins ensure adequate risk levels for operational security.

The change will result in a generally larger Flow-based domain with expected welfare gain. The change will be implemented in the Flow-based calculation from EDD 27.05.26.

The graph below shows the new FRM levels for the 29 critical grid elements: