The implementation timeline for a flow-based method for capacity calculation is dependent on successful parallel runs and confirmation from the Nordic NRAs. The parallel operations have been divided into phases (parallel runs).
Each phase has TSO-defined entry criteria, based on the guidance from NRAs. The entry criteria for the EPR start have been set. Entry criteria for each phase is the same as the exit criteria for the previous phase. More information on the criteria for the External parallel run (pdf)
According to stipulated timeline, the external parallel operation must last for at least 12 months. The NRA reporting consists of three month of data.
External parallel run have started
The Nordic TSOs and the Nordic RSC jointly decided to start the external parallel run (EPR) of the Nordic flow-based methodology on 7 March 2022 for the Energy Delivery Day of 8 March 2022.
Please note that the parallel run will generate data that can used as a basis to facilitate the adaptation of planning tools and/or business processes of all stakeholders concerned.
External parallel run data
During the EPR, the flow-based parameters will be calculated and published daily on the JAO publication tool website: https://test-publicationtool.jao.eu/nordic. Also, results from the first market simulations are now available.
Market reports
External Parallel Run - CCM Market report week 12, 2022
External Parallel Run - CCM Market report week 11, 2022
External Parallel Run - CCM Market report 2022 week 10, 2022 (updated 12 May 2022)
SF output data: physical flows, prices and net positions from simulation results of the Nordic flow-based market coupling
Update on 31 May 2022: Please note that the physical flow data and scheduled exchanges data has been removed from the result files for weeks 10 to 15 due to an error. We are investigating the root cause and will provide you with an update as soon as we have resolved the issue. We apologise for the inconvenience.
ATCE-results
ATCE week10 (updated 9 May 2022)
Input to market simulations
FB Backup domains (week 10 to week 20)
External parallel run phenomena reports
Internal parallel run data
Flow-based parameters
The flow-based parameters from the internal parallel run are available on the JAO website: https://test-publicationtool.jao.eu/nordic
There you can also find the Publication Handbook: Nordic - Publication Tool for DA CCM: https://test-publicationtool.jao.eu/app/downloads/Nordic_PublicationTool_Handbook.pdf
Internal Parallel Run Market Reports
Internal Parallel Run - CCM Market report W. 4-6, 2022
Internal Parallel Run - CCM Market report W. 1-3, 2022
Internal Parallel Run - CCM Market report W. 51-52, 2021
Internal Parallel Run - CCM Market report W. 49-50, 2021
Internal Parallel Run - CCM Market report W. 40-43, 2021
Internal Parallel Run - CCM Market report W. 35-36, 2021
ATCE results
ATCE week 49-52, 2021, p1 (excel)
ATCE week 49-52, 2021, p2 (excel)
ATCE week 49-52, 2021, p3 (excel)
Simulation data related to development of the Nordic Capacity Calculation Methodology
For information on results from comparative simulations during development of the Nordic Capacity Calculation Methodology, please visit the Methodology section.
Questions or comments?
Please address any questions or comments to CCM@nordic-rsc.net.